Also technologies have an expiration date. In 2015, Siemens will have discontinued the products of the SIMATIC S5 series. Deliveries of spare parts or compatible technologies will no longer be possible.
Also, specialists in the field of S5 products will be a rarity. To help you meet the challenges of the growing market, we support you in modernizing your technical systems. Migration is the conversion of software and hardware to a new system. Depending on your needs, your functionalities will be retained and, if necessary, optimizations will be carried out.

Coordinated with your planning and your existing plant control, such a migration can also be carried out step by step. Your way to the new technology:

Your advantages:

  • improving production capacity
  • Increasing productivity and product quality
  • availability of spare parts and experts
  • Easier work for your own maintenance staff
  • Fulfillment of current standards and regulations
  • Analysis of your existing investment
  • Determining Your Goal
  • Conversion of the controllers with local and decentralized I/Os
  • Exchange of visualization systems and computing technology
  • Adjusting the network type and its associated components
  • Translation of the existing software into the current system language
  • Execution of optimizations
  • Training of operators in the new technology

Retrofit of the engine management modules of various ABB MNS switchgear

Project Description

Migration of the ABB INSUM motor modules for various plug-in modules of the ABB MNS switchgear.

Between 2 and 22 plug-in units in sizes 1A (MO302) – 250A (MO511) of the ABB MNS series have been converted per switchboard. It also special applications such as reversing, with emergency stop and dual drive came into play. To control and manage the bays, the existing BA501 was converted to a solution with Siemens PLC control. The software stored in the PLC works intuitively for all variants. Thus, there is only one software for all switchgear sizes and variants.

project data

  • Design of the required material.
  • Collection of the corresponding reserve bays by the client. If this is not possible, as there are not enough bays in reserve, there will be a conversion on site. Ideally, in the case of a conversion in the downtime. Then the bays are moved to the IBAR headquarters for conversion.
  • Test of finished inserts on the IBAR test bench. This was created especially for this purpose with separate test PLCs.
  • Inserting the converted bays and commissioning.
  • Documentation according to the guideline of the AG with redevidation of the circuit books.
  • Preparation of a manual for system operation

Used software

  • Siemens SIMATIC STEP 7 Professional V13 SP1
  • Siemens SIMATIC WinCC Advanced V13 SP1

Used hardware

  • Siemens SIMATIC S7-IM CPU
  • Siemens SIMATIC HMI, KTP400, BASIC PANEL
  • Siemens SIMOCODE PRO V Incl. current detection in various sizes

Retrofit der Umschaltautomatiken diverser ABB MNS Schaltanlagen

Project description

Migration of the ABB Procontic CS31 control for the automatic switching of the ABB MNS switchgear.

In each case, two associated switchgear units of the ABB MNS series were migrated. In particular, the programmable logic controllers of type ABB CS31, which are responsible for monitoring the switchover.

Used software

  • ABB AC31
  • Siemens SIMATIC STEP 7 Professional V13 SP1
  • Siemens SIMATIC WinCC Advanced V13 SP1

Used hardware

  • Siemens SIMATIC S7-1200, KOMPAKT CPU
  • Siemens SIMATIC ET 200SP (remote peripherals in the switchgear fields)
  • Siemens SIMATIC HMI, KTP700, BASIC PANEL

project data

  • Reading out the configuration (programming) of the old ABB CS31 controller and converting it to Siemens S7.
  • Re-projecting the images and messages for the panel to be used.
  • Retrofit the old ABB CS31 controllers including the old system bus to the ABB periphery.
  • Assembly of new Siemens S7-1200 controllers incl. Remote peripherals and 7 “panels in the switchgear instead of the ABB controllers.
  • Rewiring of the bus line (PROFINET) between the relevant switchgear for the connection of the PLC controls and within this for the connection of the remote periphery.
  • Retrofit cross-communication between the controllers for data exchange and to detect the changeover request.
  • Documentation according to the guideline of the AG with redevidation of the circuit books.
  • Preparation of a manual for plant operation

Retrofit of the building control system DDC3000 (Kieback & Peter) to SIMATIC S7

Project description:

In the new main building of IBAR Systemtechnik, an old building control system by Kieback & Peter (DDC3000) was installed from the preliminary use by the Bundesbank. Due to the poor documentation and the limited maintenance options (only possible here by Kieback & Peter), it was decided to replace the system with a Siemens SIMATIC S7 controller.

The DDC3000 system was designed so that all substations communicated via the system’s own buses and connected to the GLT visualization system Neutrino via a central interface.

The overall concept of the old system was analyzed and restructured. The at Kieback & amp; Peter system used M, K and Z buses were replaced by the industrial bus Profinet. The central control system was an S7-1500. All subsystems were connected to the S7-1500 via ET200SP and Profinet IM.